SAMES was subcontracted to provide over 43,000 tons of asphalt and 1,500 cubic yards of concrete roadway repairs at select locations throughout the government owned plant. The goal was to provide a complete, integrated and functional installation constructed in accordance with the statement of work, and all contract and design documents in a highly secure environment.
Scope of work included heavy duty and light duty asphalt and concrete pavement repair, base or overlay asphalt repair and resurface, mill and fill pavement repair. SAMES was the first-tier subcontractor contracted by the M&O Contractor for the plant and so held complete project control and responsibility. SAMES managed all construction trades necessary for the fulfillment of the work ensuring the work was performed in accordance with all contract documents and in compliance with all applicable local, state and federal regulations.
SAMES self-performed concrete, drainage, striping, traffic control, restoration of disturbed areas, and grading. The SAMES team completed over 90% of the paving operations and 95% of the total contract within 120 days.